Somerton Embankment
Client: Birse Rail Value: £300,000 Duration: 8 weeks
Slope stabilisation including soil nails, site clearance, earthworks and drainage. Gabion works were undertaken between the the existing railway and canal infrastructure
Harvil Road Embankment, London
Client: Birse Rail Value: £250,000 Duration: 16 weeks
Design & build stabilisation of failed embankment for Network Rail including site clearance, earthworks, drainage, soil nailing, surface protection and track-side monitoring
Channel Tunnel Rail Link - 440
Client: Balfour Beatty Value: £380,000 Duration: 10 weeks
Design, supply and installation of 28m long ground anchors to secure sheet piled wall. Also to supply and install soil nails and netting.